Most jobs that overrun do not overrun on the digging. They overrun on getting rid of what came out of the hole.
Spoil is heavier, bulkier and more expensive to move than people expect, and it is the one part of a groundworks job that is easy to work out in advance on the back of an envelope. Ten minutes with a tape measure and a calculator will tell you what dumper you need, how many lorry loads you are paying for and how long to book the machine.
Here is the method we talk customers through on the phone.
Step One: Work Out the Dig Volume
Length times width times depth, all in metres, gives you cubic metres. That is your in-situ volume, meaning the material as it currently sits in the ground.
For a trench, use the trench length rather than the building perimeter if the trench runs in a line. For a foundation running round a building, use the perimeter.
Keep everything in metres and it stays simple. A trench 600mm wide is 0.6m. A dig 1.2m deep is 1.2m.
Step Two: Add the Bulking Factor
This is the step people miss, and it is the one that causes the problem.
Material swells when you dig it out. Break up ground that has been compacted for centuries and it will not go back into the same space. The increase is called the bulking factor, and it varies with what you are digging:
- Sand and gravel, roughly 1.1 to 1.15 times
- Topsoil, roughly 1.2 to 1.3 times
- Clay, roughly 1.3 to 1.4 times
- Chalk, roughly 1.4 to 1.5 times
- Broken rock, 1.5 times and upwards
So 15 cubic metres of clay in the ground becomes roughly 20 cubic metres in a heap. If you priced your muck away on the in-situ figure, you are already a quarter short.
Step Three: Convert to Tonnes
Grab lorries and tipper wagons charge by weight, and weight is what limits them. As a rough guide for in-situ material:
- Topsoil, around 1.3 to 1.5 tonnes per cubic metre
- Clay, around 1.8 to 2.0 tonnes per cubic metre
- Sand and gravel, around 1.6 to 1.8 tonnes per cubic metre
- Hardcore and Type 1, around 1.8 to 2.0 tonnes per cubic metre
Wet material is heavier than dry. If you are digging clay in February, work to the top of the range.
A Worked Example
Say you are putting strip footings in for a detached garage, 8m by 5m on plan, in clay.
The trench runs round the perimeter, so 2 times 8 plus 5, which is 26m. At 600mm wide and 1m deep, that is 26 times 0.6 times 1.0, giving 15.6 cubic metres in the ground.
Apply a clay bulking factor of 1.3 and you have around 20 cubic metres of loose spoil sitting on your site.
At 1.8 tonnes per cubic metre in situ, that is roughly 28 tonnes of material to shift.
Now the hire decisions fall out of it. A 3 tonne dumper carries somewhere around 1.7 cubic metres heaped, so you are looking at roughly a dozen runs to move it clear of the trench. Two grab lorry loads at 16 tonnes will take it off site. And you know the machine is on hire long enough to dig, load and tidy, not just dig.
Matching the Dumper to the Job
Once you know the volume, picking the dumper is straightforward. As a general guide, a 1 tonne dumper carries around half a cubic metre, a 3 tonne around 1.7, a 6 tonne around 3, and a 9 tonne around 5.
The temptation is always to take the biggest dumper available. Resist it if your access is tight or your ground is soft. A machine that cannot get where you need it is worth nothing, and a big dumper that churns your route into a bog will cost you more time than it saves. On soft or sloping ground a tracked dumper will often outperform a larger wheeled one.
Where Is It All Going?
Two questions worth settling before you dig rather than after.
Can any of it stay? Clean subsoil can often be regraded or used to build up levels elsewhere on the plot, which removes tipping cost entirely. Topsoil is worth stripping and stockpiling separately if there is any landscaping to come.
Is it contaminated? Made ground, old industrial sites and anything with asbestos, tarmac or fuel contamination changes the disposal route and the price completely. If you have any doubt, get it tested before you book a grab lorry, not after it arrives.
Get the Machine and the Dumper Right
Work out the volume first and the rest of the hire falls into place. If you would rather talk it through, tell us the dimensions of the dig and what you are digging into, and we will help you size both the excavator and the dumper.
Call 01285 862222 or email hire@bisonplanthire.com.
More from the yard. Guides and news.
5 Common Plant Hire Mistakes and How to Avoid Them
Plant hire is an excellent way to access high-quality equipment for your construction projects, but it’s not w…
FAQs About Plant Hire: Everything You Need to Know Before Renting Equipment
Plant hire can be a game-changer for your construction project, but if you’re new to the process, you might ha…
The Best Plant Hire Equipment for Road and Highway Projects
Road and highway construction projects require specialised machinery to ensure efficiency and safety.…
Open a credit account. Hire on terms.
Simple monthly terms for contractors and repeat trade, the most efficient way to keep machines on site across the South West.